About this manual#
This manual teaches steady-state hydraulic calculation with FlowMax by working twelve cases from start to finish. The first three are small and establish how the program is driven. The other nine are the kind of case a process, piping or fire protection engineer is actually handed. Each one is a complete project file that can be opened, run and changed.
The examples are also where the analysis tools are taught. A scenario, a goal seek, a formula, a graph or a results table on the sheet is introduced in the example where an engineer would reach for it, and is then used again in later examples without being explained twice. The analysis tools, and where each is taught lists which example introduces which tool.
| Example | Case | FlowMax features it introduces or uses | The engineering lesson |
|---|---|---|---|
| 1 | Three pipes and a tee | Pipes, nodes, fittings from the library, the table of the selected element, tables on the sheet, a first Sets scenario | Where the pressure goes: friction, fittings and static head |
| 2 | A pump, sized and then rated | Tanks, pump sizing and rating modes, control valve, Graphs (pump against system), Adjust | What throttling costs, and what speed control saves |
| 3 | Cooling water circuit | Exchangers, flow control valves, Links and Nodes tables, Calculator, Sets scenario | Balancing, and the limit of a control valve |
| 4 | Chilled water distribution | Pipe Sizing module, load cases as a scenario chosen on the Home page, Adjust on pump speed | Sizing by criteria, then part-load behaviour |
| 5 | Gasoline transfer pipeline | Library fluid, two pump stations, Graphs (path graph), Calculator as a scenario result | The hydraulic profile of a line that climbs |
| 6 | Fire water ring main | Looped network, pump and pipe status, five fire cases as a scenario, Adjust on a demand | What a ring is worth, and what is lost when part of it is shut |
| 7 | Spray systems on two tanks | Hazen-Williams, Nozzle Layout (auto layout, insert, sizing), Adjust on the supply pressure | Laying out and proving a spray system |
| 8 | LNG rundown line | Library fluid and pipe material, path graph, Calculator, scenario on the rundown rate | Keeping a boiling liquid above its bubble point |
| 9 | Three pumps in parallel | Pumps on and off as a scenario, NPSH required curve, warnings, scenario on a pipe size | Why one pump alone runs out, and the NPSH problem that brings |
| 10 | Warehouse sprinklers, NFPA 13 | The isometric sheet, sprinklers by K factor, tees and elbows with NFPA equivalent lengths, Adjust, the NFPA calculation and graph of the report | Is the town main enough for the remote area |
| 11 | Deluge on a horizontal drum, NFPA 15 | Fittings lists in Hazen-Williams, Adjust on the take-off, a restriction orifice by ISO 5167 | What a deluge system needs, and what it takes when given more |
| 12 | Fire pump and standpipes, NFPA 20 and 14 | A pump in a Sets scenario of its acceptance test, a pressure-reducing valve, Calculator, Adjust on pump speed | The pump's test points, the top outlet and the bottom one |
How each example is written#
Every example has the same twelve numbered parts: objective, engineering problem, model schematic, input data, model set-up, calculation procedure, reference results, interpretation, what-if investigation, comparison, engineering remarks and exercise. An example can therefore be used on its own, and the same question is always answered in the same place.
Reading the figures and the numbers#
- Every figure is FlowMax itself: its flowsheet, its windows and its tables, painted from the project file the example names. Nothing in a figure was drawn for the manual, so what is on the page is what will be on the screen.
- On a results sheet the figure above a pipe is its flow and the figure at a node is its pressure, as chosen in the Links and Nodes selectors at the top right of the window. Each caption says what is shown.
- A red numbered circle on a window marks a field the caption refers to.
- FlowMax shows results to four significant figures by default. The text quotes the same numbers to two decimal places; both are the same result.
- A reader's own model should reproduce a reference result to within 1 per cent on flow and 0.05 bar on pressure. A larger difference means an input differs, and the input tables are the place to look.
Licence A FlowMax Lite licence solves models of up to 40 links. Every model in this manual has 33 or fewer, so all of them run on it.
Display The project files are saved with the flowsheet label size at 12, or at 10 where the model is crowded. FlowMax fits a project to the window when it is opened, so the same file looks larger or smaller on a different screen; the Scale box on the Home page changes it.
The FlowMax workspace#
This chapter is a map. It names the parts of the window and the tools on the ribbon, and says in which example each is put to work. Nothing here needs to be learned before starting Example 1; it is the place to come back to.
The window#

- The ribbon has the pages Home, Tools, Transient and Reports, and every button on it carries its name. This manual uses all of them except Transient, which belongs to transient analysis.
- The Equipment strip down the left edge holds everything that is placed on the sheet: pipes, pumps, valves, tanks, fittings, text and tables. Press a square, then click on the sheet. Resting the mouse on a square shows its name.
- The Links and Nodes selectors choose what is written beside every link and node on the sheet. Each has two boxes, for the label above and the label below.
- The flowsheet is where the model is drawn. Double-click an element to open its property window.
- The panel at the right has two pages. Properties is the table of the selected element: it lists the inputs of whatever is selected and, after a run, its results. It is the quickest way to read one element, and it is first used in Example 1. Elements lists every element of the model by kind, with a box to find one by name: a click on a line points the element out on the sheet, a double click opens it. The word Elements under the Equipment strip opens the panel on that page.
- The status bar says whether the model is ready to run, solved, or solved with warnings or errors.
The ribbon pages#




What a model is made of#
A FlowMax model is links joined at nodes. A link is anything that carries flow and loses or gains pressure doing it: a pipe, a pump, a valve, a general pressure drop, an exchanger, a spray nozzle. A node is a point where links meet, and is where pressure is reported.
A network can be solved only if enough is known at its edges, and the rule is the same in every hydraulic program:
- At least one node must have a known pressure. Without one every pressure could be shifted by the same amount and no flow would change.
- Every other boundary is a known pressure or a known flow. A flow leaving the network is entered as a negative Flow In; a flow entering is positive.
- A tank is a known pressure in disguise: its surface pressure, liquid level and elevation fix the head at its outlet.
Four ways to read results#
| Where | What it gives | First used |
|---|---|---|
| Labels on the sheet | One or two values beside every link and node, chosen in the Links and Nodes selectors | Example 1 |
| The table of the selected element | Every input and result of one element | Example 1 |
| A table on the sheet (Table, on the Equipment strip) | Chosen results of chosen elements, kept on the drawing and updated by every run and by every case selected | Example 1 |
| Links table and Nodes table (Home page) | Every element of one kind, one row each | Example 3 |
The analysis tools, and where each is taught#
| Tool | What it does | Introduced | Used again |
|---|---|---|---|
| Scenario (Sets) | Runs the model for a list of cases, each a set of typed input values, and tabulates chosen results. With Enable case selection ticked, a case can then be chosen on the Home page and the whole sheet shows it. | Example 1 | 3, 4, 5, 6, 8, 9, 12 |
| Adjust | Goal seek: varies one input until one result reaches a target value. | Example 2 | 4, 6, 7, 10, 11, 12 |
| Graphs | A pump against the system it works into, or any result along a path of links. | Example 2 | 5, 8, 9 |
| Calculator | Named formulas in the model's own results, recalculated by every run. | Example 3 | 5, 6, 7, 8, 9, 10, 11, 12 |
| Table (Equipment strip) | A results table drawn on the flowsheet. | Example 1 | all |
| Sizing | Chooses pipe sizes from a schedule to meet velocity and friction limits. | Example 4 | |
| Nozzle Layout | Lays out spray nozzles on a tank, then inserts the nozzles and their sized pipework into the model. | Example 7 | |
| Fittings & Pipe Losses | Elbows, tees and valves chosen from the library for one pipe; equivalent lengths in a Hazen-Williams project. | Example 1 | 4, 5, 6, 8, 9, 10, 11, 12 |
| Drawing mode (right-click on the sheet) | The isometric sheet: nodes on a lattice of 30 degree lines. | Example 10 | 11, 12 |
| Report, NFPA 13 / 15 calculation | The calculation in NFPA's form in the PDF report, with the water supply against the demand. | Example 10 | 11 |
Base scenario The tools that change the model - Scenario, Adjust, Sizing - work on the base case. If the case selector on the Home page shows a case, set it back to Base Scenario first; the program says so if it is forgotten.
Example 1 Three pipes and a tee#
Project file 01_3 Pipes.flmx
1.1 Objective#
To build the smallest network whose answer cannot be seen by inspection, run it, and read the result four ways. By the end the reader will be able to enter pipes, nodes and fittings, say where pressure and flow are known, read the result from the sheet, from the table of the selected element and from a table placed on the sheet, and run a first scenario.
1.2 Engineering problem#
A supply main at a known pressure feeds a tee. One branch runs to a consumer at grade; the other runs further, to a consumer nine metres up, through an elbow, an isolating gate valve and a ball check valve. Both consumers take a fixed flow. What pressure is left at each of them?
The flows are given, so they are arithmetic. What is not given is the pressure that arrives, and that is made up of three costs that behave differently: friction and fittings, which go as the square of the flow, and static head, which does not depend on flow at all.
1.3 Model schematic#

1.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water at 25 °C | Fluid library: 996.89 kg/m³, 0.89 cP |
| Units | m³/h, bar (absolute), m | Unit set of the project |
| N1, supply | 12.00 bar at grade | Known pressure |
| N3, consumer | 22.00 m³/h at grade | Known flow out, entered as Flow In = -22 |
| N4, consumer | 90.00 m³/h at 9.00 m | Known flow out, entered as Flow In = -90 |
| P1, supply main | 50.00 m, 100 mm bore | Commercial steel, roughness 0.0457 mm |
| P2, branch to N3 | 50.00 m, 100 mm bore | |
| P3, branch to N4 | 78.00 m, 100 mm bore | Fittings: 1 x 90° standard elbow, 1 x open gate valve, 1 x ball check valve |
1.5 Model set-up#
The fluid. Press Fluid Properties on the Home page. Water is chosen from the library and its temperature typed; density, viscosity and vapour pressure follow.

The pipes. Double-click P3. Its bore is typed rather than taken from a schedule, which FlowMax allows; a schedule is the normal choice on a real job and is used from Example 2 onwards.

The fittings. The loss in bends and valves is not entered as a number. Press Details Fittings in the pipe window to open Fittings & Pipe Losses, choose each fitting in the upper list and press Add; the quantity can be typed in the lower list. FlowMax keeps the list with the pipe and writes the total into the K factor. (Ticking Specify instead lets a K be typed directly.)

The ball check valve is by far the largest resistance in the model. At 90 m³/h the velocity in P3 is 3.18 m/s and one velocity head is 0.0505 bar, so the check valve alone costs 3.54 bar. The what-if in section 1.9 asks what a different valve would cost.
The nodes. A node is told what is known about it. N1 is given a pressure; N3 and N4 are given flows. A flow leaving the network is negative.


Enough is known One pressure and two flows. The supply flow at N1 does not have to be given: it is whatever the two demands add up to.
1.6 Calculation procedure#
- Open 01_3 Pipes.flmx, or build the model from Table 4.
- Press Run on the Home page. The status bar changes to Solved.
- In the Links selector at the top right choose Flowrate for the upper label, and in the Nodes selector choose Pressure. The sheet now carries the results.
- Click P3. Its table opens at the right of the window (Figure 14).
- To put results on the drawing itself, press Table on the Equipment strip and click where the table is to stand. In the Add Table window (Figure 12) choose the kind of element at the top right, move the elements wanted to the right-hand list with >, do the same for the variables, give the table a title and press Add.

1.7 Reference results#


The values to check a model against are in the two tables on the sheet: N2 11.31 bar, N3 11.28 bar and N4 6.15 bar; pressure drops of 0.69, 0.03 and 5.17 bar in P1, P2 and P3.
1.8 Interpretation#
The supply carries 112.00 m³/h, the two demands added together. The two consumers, fed from the same tee, are 5.13 bar apart. The table of P3 says why: of its 5.17 bar, 0.88 bar is static head for the nine metre rise and 4.29 bar is friction and fittings together - of which the fittings are 3.58 bar and the 78 m of pipe only 0.70 bar.
The branch that costs the most is therefore not the one carrying the most flow: P1 carries 112 m³/h and loses 0.69 bar. And most of what P3 loses would not be recovered by a larger pipe.
1.9 What-if investigation#
What would a different check valve be worth? The library gives a swing check valve a K of 2.00 against 70.00 for the ball check, so the fittings total would be 2.92; with no check valve at all it would be 0.92. Rather than editing the pipe three times, the three values are run as a scenario.
- Press Scenario on the Tools page. The Scenario Manager opens (Figure 15); Add scenario makes a new page. Leave Scenario type at Sets.
- Press Select variable, and in the window that opens choose the pipe P3 and its Fitting K value and move it across with >. Close it with Select variables.
- Press Add variable under Output variables and choose, the same way, the pressure drop of P3 and the pressures of N2 and N4.
- Press Add case three times: each press adds a row to the Results table, starting from the value the model has. Type the K value of each case in the blue cells - 70.92, 2.92 and 0.92 - and press Run.
- Tick Enable case selection and close the window.

Duplicate copies the selected case and Remove case takes it away. A case is given a name by typing over case1 in the first column; the case selector of the Home page then lists it by that name. Apply to model writes the inputs of the selected case into the model, which then is that case: it asks first, and the results on the sheet are cleared until the next Run.
1.10 Comparison#
The Results table of Figure 15 is the comparison: N4 has 6.15 bar with the ball check valve, 9.58 bar with a swing check and 9.68 bar with none. The choice of check valve is worth 3.43 bar at the consumer; removing it altogether adds only another 0.10 bar.
Because case selection is enabled, the cases can also be looked at on the sheet. The selector at the left of the Home page now lists Base Scenario, Case-1, Case-2 and Case-3. Choose Case-2 and everything on the sheet - labels, the table of the selected element and both tables - shows that case.


1.11 Engineering remarks#
- A K factor taken from a library is a typical value for a fully open fitting of ordinary pattern. For a component that decides the answer, as the check valve does here, use the manufacturer's figure and type it as an Additional K Factor in the same window.
- The model is isothermal and the fluid incompressible. That is right for water in a short line and is the assumption throughout this manual.
- A scenario does not change the model. The base case is still the ball check valve; to adopt another valve, edit the fittings of P3.
- Set the case selector back to Base Scenario before editing or running: the tools that change the model work on the base case only.
1.12 Exercise#
The consumer at N4 needs at least 8.00 bar. With the ball check valve kept, find the largest flow N4 can take. Add a second scenario page with the Flow In of N4 as the input and the pressure of N4 as the output, try -60, -70 and -80 m³/h, and narrow it down. (The answer is 70.59 m³/h. Example 2 introduces Adjust, which finds such a value directly.)
Example 2 A pump, sized and then rated#
Project files 02_Pump Sizing part 1.flmx 02_Pump Rating part 2.flmx 02_Pump Rating part 3 (speed control).flmx
2.1 Objective#
To find the head a pump must produce for a duty, then to put a real pump curve into the same model and find what that pump delivers, what its control valve has to destroy, and what speed control would save. The example introduces tanks, the two pump calculation modes, the control valve, the Graphs tool and the Adjust tool.
2.2 Engineering problem#
Water is to be transferred at 100 m³/h from an open tank at grade to a vessel held at 8 bar, five metres up, through 200 m of 6 inch pipe and a control valve. No pump has been bought yet. The first question is what the pump must do; the second, once a pump has been chosen from a catalogue, is how the installation then behaves.
2.3 Model schematic#

2.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water at 25 °C | Fluid library |
| Units | m³/h, bar (absolute), m | Unit set of the project |
| Tank2, suction | Open to atmosphere, 1.01 bar, at grade | Known pressure |
| Tank1, delivery | 8.00 bar on the surface; base at 5.00 m, level 5.00 m | Known pressure |
| P1 to P4 | 50.00 m each, 6 inch schedule 40 | Commercial steel |
| Pump1, part 1 | Sizing mode, flow 100.00 m³/h | The duty asked for |
| Valve1, part 1 | Control target Pressure drop, 1.00 bar | Margin allowed for control |
| Pump1, parts 2 and 3 | Rating mode, curve through 100 m³/h at 100 m | Catalogue pump |
| Valve1, part 2 | Control target Flowrate, 100.00 m³/h | Flow controller |
| Valve1, part 3 | Control target None, opening 100 % | Valve left wide open |
2.5 Model set-up#

Part 1, sizing. With no curve there is no duty point to find, so the question is turned round: the pump is told the flow and FlowMax reports the head that flow needs. The valve is told to lose one bar, which is the control margin being bought deliberately.


Part 2, rating. The pump is given the curve of the machine chosen. Press Enter data in the pump window to type the curve points. The valve stops being a stated loss and becomes a flow controller: the drop it needs is now a result.


2.6 Calculation procedure#
- Open 02_Pump Sizing part 1.flmx and press Run. Read the head required from the table on the sheet or by clicking the pump.
- Open 02_Pump Rating part 2.flmx and press Run. Compare.
- On the Tools page press Graphs. The file holds one graph of type Pump-system curve for Pump1; Generate draws it. To make one from nothing: Add Graph, set Graph type to Pump-system curve, press Select pump, choose the pump, Generate.
- Open 02_Pump Rating part 3 (speed control).flmx for the what-if of section 2.9.
2.7 Reference results#




2.8 Interpretation#
Sizing asked for 94.21 m. No catalogue pump has exactly that, and the one chosen gives 100.00 m at the duty flow. The extra 5.79 m does not disappear: the flow is held at 100 m³/h, so the control valve has to absorb it, and its drop goes from the 1.00 bar that was planned to 1.57 bar. The shaft power is 36.22 kW at an efficiency of 75.0 per cent; the 25.59 kW reported in part 1 is hydraulic power only, because a pump with no curve has no efficiency.
NPSH available at the pump is 9.40 m, which is ample: the suction tank is open and the suction line short. Example 9 is the example where it is not.
2.9 What-if investigation#
What does the control valve cost, and what would a variable-speed drive save? In the third file the valve is left wide open. Run it: with nothing to hold it back the pump moves out along its curve to 120.41 m³/h. The pump-system curve shows the new crossing.

The duty is still 100 m³/h. The speed that gives it is found with Adjust, which varies one input until one result reaches a target.
- Press Adjust on the Tools page, then Add Adjust.
- Under Adjusted variable press Select variable and choose Pump1, Relative speed.
- Under Target press Select variable and choose Pump1, Flowrate. Type 100 as the Target value.
- Press Start. The iterations are listed as they are made.
- Press Apply Solution to write the speed found into the pump.

2.10 Comparison#
| Throttled, full speed | Valve open, speed 0.945 | |
|---|---|---|
| Relative speed | 1.000 | 0.945 |
| Pump head (m) | 100.00 | 86.55 |
| Valve pressure drop (bar) | 1.57 | 0.25 |
| Shaft power (kW) | 36.22 | 31.41 |
At 94.5 per cent speed the pump delivers the same 100 m³/h with the valve open, and the shaft power falls from 36.22 to 31.41 kW: 4.82 kW, or 13 per cent, is what the throttled valve was costing.
2.11 Engineering remarks#
- A sizing run gives the head and flow to take to a pump supplier. It does not give the shaft power, the NPSH required or the shape of the curve; all three come with the pump.
- Speed control changes the curve by the affinity laws. FlowMax applies them when Relative speed is changed; the efficiency is read from the curve at the equivalent flow.
- Adjust needs a target the adjusted variable can actually reach. If Start reports Failed, widen the question: check the target value, or give a Minimum and Maximum.
- The pump-system curve is drawn for a pump in Rating mode, and the model must be solved first.
2.12 Exercise#
The delivery vessel is to be operated at 9 bar instead of 8. In part 2, change the Tank pressure of Tank1 and run. Does the valve still control - is its opening below 100 per cent - and what is its pressure drop now? Then use Adjust to find the vessel pressure at which the valve is left with 0.50 bar (adjusted variable: Tank1, Tank pressure; target: Valve1, Pressure drop; target value 0.5). The answer is 9.07 bar.
Example 3 A cooling water circuit#
Project files 03_Cooling Water part1.flmx 03_Cooling Water part2 (control valve).flmx
3.1 Objective#
To model a closed circuit serving four heat exchangers, to see how unevenly it shares the flow when nothing controls it, and to balance it with flow control valves. The example introduces the Exchanger, the Links table and Nodes table, the Calculator, and uses a scenario to find where a control valve runs out.
3.2 Engineering problem#
One pump circulates cooling water from a tank, through a supply header that reduces in size as it sheds flow, to four exchangers with design duties of 50, 25, 30 and 10 m³/h, and back to the same tank through a return header. Each exchanger loses 1 bar at its design flow. Does each one get its flow?
3.3 Model schematic#

3.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water at 25 °C | Fluid library |
| Units | m³/h, barg, m | Gauge pressure, so an open tank reads zero |
| Tank1 | Open, base at 20.00 m, level 1.00 m | The only known pressure |
| Pump1 | Rating mode; curve through 150 m³/h at 34 m | |
| E1 to E4 | 1.00 bar at 50, 25, 30 and 10 m³/h; Required flow the same | Exchanger data sheets (reference flow and reference pressure drop); the design duty |
| Headers | 6 inch; 200 m from the pump, 10 m between branches | Schedule 40 |
| Branches | 4, 3, 3 and 2 inch, 10 m each way | Schedule 40 |
| Valve1 to Valve4, part 2 | Control target Flowrate, set to the design duty |
3.5 Model set-up#
A heat exchanger is not a pipe. It is entered as an Exchanger, the button after the flow meter on the Equipment strip, by one point from its data sheet: a reference flow and the pressure drop at that flow. FlowMax scales the drop with the square of the flow, as for a PD element. The Required flow is the flow the exchanger is designed for; it is optional, and when it is given FlowMax reports how far the flow found is above it, as Overdesign. The Heat Transfer tab is used only when the fluid has variable properties.


A closed circuit has no source and no sink. The tank is the only boundary, and the pump moves what is already in it.
3.6 Calculation procedure#
- Open 03_Cooling Water part1.flmx and press Run.
- Press Links table on the Home page. Choose the kind of element in the box at its top left; every element of that kind is listed, one row each (Figure 33). Nodes table does the same for nodes.
- Press Calculator on the Tools page (Figure 35). To make a calculation from nothing: Add variable, choose the elements and results wanted, which become var1, var2 and so on; then type a Name and a formula in those variables and press Add. The formula turns green when it can be worked out.
- Open 03_Cooling Water part2 (control valve).flmx, run it, and open the Calculator again.

The Exchanger tab of the Links table lists the four exchangers with their Required flow and their Overdesign, the per cent by which the flow found is above the required one.
3.7 Reference results#



3.8 Interpretation#
With nothing to control it the circuit takes 152.05 m³/h against a design total of 115. The Calculator says how it is shared: every exchanger is between 31 and 33 per cent over its design flow. The pump was selected with margin, the exchangers are the only real resistance, and the margin becomes flow.
With the valves in, every exchanger has its design flow and the pump moves back up its curve to 37.50 m. The four valves take about 1.76 bar each at about 50 per cent open. The shaft power falls from 18.63 to 16.55 kW because less water is moved, but the power per 100 m³/h delivered rises from 12.25 to 14.39 kW: balancing by throttling is paid for in head.
3.9 What-if investigation#
The first exchanger is to be uprated. How much more flow can its valve give it before the valve is wide open? In part 2 a scenario of type Sets raises the set point of Valve1 from 50 to 80 m³/h in four cases and records the valve's opening and pressure drop.


3.10 Comparison#
At 60 m³/h Valve1 is 77 per cent open with 1.06 bar across it: it still controls. At 70 m³/h the table shows an opening of 182 per cent. An opening above 100 is FlowMax saying that the valve would have to be larger than it is to pass that flow: the duty is beyond this circuit, and the run is flagged with a warning. At 80 m³/h the pressure drop reported is negative, which is not a result at all but the sign that the case has no solution. The limit lies between 60 and 70 m³/h.
3.11 Engineering remarks#
- An exchanger, like a PD element, reproduces one data sheet point and a square law. It is right for an exchanger, a strainer or a filter in turbulent flow, and should not be stretched far from its reference flow.
- A flow control valve in a steady-state model always achieves its set point if it can. Always read its opening: below about 10 per cent or above about 90 it is not controlling in practice.
- A case that cannot be solved shows up in a scenario as an impossible value, not as an error message. Read the table before quoting from it.
- The Calculator is recalculated by every run and its results can be put on the sheet (Table on the Equipment strip, element kind Calculator) and used as scenario outputs.
3.12 Exercise#
Add a calculation to part 2 for the hydraulic power destroyed in the four control valves. The power lost in a valve in kW is its flow in m³/h times its pressure drop in bar, divided by 36. Add the four valve flows and pressure drops as variables and write the formula. What fraction of the pump's shaft power is being thrown away in the valves?
Example 4 Chilled water distribution#
Project files 04_Chilled Water - before sizing.flmx 04_Chilled Water.flmx 04_Chilled Water - normal load.flmx
4.1 Objective#
To size the pipework of a closed chilled water circuit with the Sizing tool, to examine the sized circuit at three load cases held in one file as a scenario and chosen from the Home page, and to find with Adjust the pump speed the circuit actually needs at normal load.
4.2 Engineering problem#
A four-storey building is served by two chillers in parallel and one circulating pump. A supply riser feeds one air handling unit on each floor; each unit has a cooling coil and a two-way control valve; a return riser brings the water back to the pump. An expansion vessel on the pump suction holds the system pressure.
What pipe sizes satisfy the project's velocity and friction limits? With those sizes, does the pump deliver the design flow to every floor? And at 60 per cent of the cooling load, where the building spends most of the year, how much of the pump's head is being thrown away in the control valves?
4.3 Model schematic#

4.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water, Variable properties | Fluid library; 7 °C from the chillers, 13 °C from the coils, each pipe at its own temperature |
| Units | m³/h, barg, m | Unit set of the project |
| EV-1, expansion vessel | 3.00 barg on 1.00 m of water | Assumed fill pressure |
| CHWP-1 | Rating mode; curve through 140 m³/h at 17.6 m | Shut-off 22.0 m, best efficiency 78 % |
| CH-1, CH-2 | PD, 0.45 bar at 70 m³/h each; outlet temperature 7 °C | Chiller data sheet |
| AHU-1 to AHU-4 | PD, 0.35 bar at design flow; outlet temperature 13 °C | Coil data sheet |
| TCV-1 to TCV-4 | Control target Flowrate | Cv twice that needed at design flow and 0.35 bar |
| Unit | Floor level (m) | Design flow (m³/h) | Normal load, 60 % (m³/h) |
|---|---|---|---|
| AHU-1 | 4.00 | 50.00 | 30.00 |
| AHU-2 | 8.00 | 40.00 | 24.00 |
| AHU-3 | 12.00 | 30.00 | 18.00 |
| AHU-4 | 16.00 | 20.00 | 12.00 |
| Total | 140.00 | 84.00 |
| Pipes | Service | Length each (m) | Fittings from the library |
|---|---|---|---|
| P1 to P4 | Chiller connections | 8.00 | none |
| S-1 | Supply main to the first floor | 35.00 | 4 x 90° standard elbow |
| S-2 to S-4, R-1 to R-4 | Risers between floors | 4.00 | none |
| B1a to B4b | Branch to and from each unit | 15.00 | 1 x branching tee, 2 x 90° standard elbow, 1 x open gate valve |
| R-0 | Return main back to the pump | 45.00 | 4 x 90° standard elbow, 1 x open gate valve |
Sizing criteria Velocity not above 2.50 m/s and friction loss not above 0.004 bar/m (400 Pa/m), schedule 40 steel. These are the limits assumed for this example; a real project takes them from its own design basis.
4.5 Model set-up#
The model is first built with every pipe at 6 inch. Nothing about that guess matters except that the model solves: the control valves fix the flow in every branch, so the flows the sizing needs are right whatever the pipes are.





The water is given at its temperature. In the Fluid window Variable properties is chosen, the fluid water from the library. Each chiller and each coil is an exchanger: on the Heat Transfer tab of CH-1 and CH-2 the outlet temperature is 7 °C, on each coil's 13 °C, and the expansion vessel's water is at 13 °C. The Run carries the temperatures round the circuit and takes the density and the viscosity of each pipe at its own temperature; the duties are results.
The branches carry their fittings as fittings, not as a number: the tee off the riser, two elbows and an isolating gate valve on each.


4.6 Calculation procedure#
- Open 04_Chilled Water - before sizing.flmx and press Run.
- On the Tools page press Sizing. The Pipe sizing window opens on its Set up tab (Figure 47). Leave Sizing Method at Simple.
- Press Select under Pipes set and choose every pipe; press Select under Diameter set and choose schedule 40.
- In the Constraints table leave Object at All pipes and type the allowable Velocity, 2.5, and the allowable Friction loss/Length, 0.004.
- Press Autosize and read the Results tab (Figure 48).
- Press Apply to write the chosen sizes into the model, then Run again.
- 04_Chilled Water.flmx is that model, sized, with the load cases of section 4.9 added.


4.7 Reference results#
The supply main S-1 comes out at 8 inch and the return main R-0 at 6 inch. The branches come to 6 inch on the lowest floor and 3 inch on the top floor, and the upper riser to 4 and 3 inch.


4.8 Interpretation#
Every unit receives its design flow and every control valve settles between 36 and 40 per cent open with 0.55 to 0.66 bar across it, against 0.35 bar for its coil: every valve has authority. Before sizing the same valves dropped 0.55 to 0.56 bar; the smaller pipes take some of the pump head and the valves give it up, which is exactly what sizing to a friction limit should do.
At peak load the four coils take 977 kW from the water and the two chillers take out 977 kW: the water leaves the chillers at 7 °C and comes back from the coils at 13 °C.
The static pressure is the other thing to read. The vessel holds 3.10 barg at the pump suction; the lowest pressure in the circuit is 1.74 barg at R4, on the return side of the top floor, and must stay comfortably positive or air is drawn in at the vents. The highest is the pump discharge at 4.83 barg, which is what the pressure rating has to cover.
4.9 What-if investigation#
The three load cases are not three files. They are one scenario of type Sets in 04_Chilled Water.flmx, with five inputs - the four valve set points and the pump's relative speed - and three cases: peak load, normal load at 60 per cent, and normal load with the pump slowed to 80 per cent.



With case selection enabled the cases are chosen on the Home page.




4.10 Comparison#
The Results table is the comparison. At normal load and full speed the pump rides back up its curve to 20.42 m. The circuit needs less head at the lower flow, not more, so the valves have to destroy the difference: the drop across TCV-4 rises from 0.55 to 1.57 bar and it closes to 14 per cent open. At 80 per cent speed the valves open again to 20 per cent and the shaft power falls from 7.30 to 4.47 kW for exactly the same cooling.
Eighty per cent was a guess. The speed the circuit needs is the one that leaves the least-favoured control valve with just enough pressure drop to control, taken here as 0.35 bar, the same as its coil. 04_Chilled Water - normal load.flmx is the sized model with the valves set to normal load, and in it an Adjust finds that speed: the adjusted variable is the relative speed of CHWP-1, the target is the pressure drop of TCV-1, the valve with the least across it, and the target value is 0.35.


| Full speed | Speed 0.659 | |
|---|---|---|
| Pump head (m) | 20.42 | 7.98 |
| Shaft power (kW) | 7.30 | 2.85 |
| TCV-1 pressure drop (bar) | 1.61 | 0.39 |
| TCV-1 opening (%) | 13.96 | 28.25 |
| TCV-4 opening (%) | 14.15 | 29.96 |
At 65.9 per cent speed the pump absorbs 2.85 kW against 7.30 kW at full speed: 61 per cent less, with every unit still receiving its flow.
4.11 Engineering remarks#
- The Simple sizing method looks at each pipe on its own, at the flow the solved model gives it. It does not check the pump. Always run again after Apply and look at the valve openings.
- The method walks up the list of candidate sizes until the constraints are met. A size missing from the schedule library is skipped: schedule 40 as supplied has no 5 inch.
- With Object set to Individual in the Constraints table, a limit is typed for each pipe in the Pipes set instead of one limit for all.
- A two-way valve is modelled as a flow controller. That is right for a design check and says nothing about how well the real valve will control; that depends on its authority, which is why its pressure drop is read.
- A scenario case that changes the pump speed uses the affinity laws, as in Example 2.
4.12 Exercise#
The top floor is to be extended, raising the design flow of AHU-4 from 20 to 30 m³/h. In 04_Chilled Water.flmx set the selector to Base Scenario, change the set point of TCV-4 and run. Is the 3 inch branch still inside the velocity and friction limits? Run the Sizing tool again on the branch pipes B4a and B4b only and see what it chooses.
Example 5 Gasoline transfer pipeline#
Project files 05_Gasoline Pipeline.flmx 05_Gasoline Pipeline - terminal valve open.flmx
5.1 Objective#
To model a long pipeline over changing ground with two pump stations, to draw its hydraulic profile with the Graphs tool, to keep the pumping energy in a Calculator, and to see with a scenario how the pressures along the line move with throughput.
5.2 Engineering problem#
Gasoline is transferred through 48 km of 12 inch line from a tank at one terminal to a tank at another. The line drops to a river crossing at 8 m and climbs over a ridge at 205 m. One pump station stands at the start and one at kilometre 24. The flow is held at 400 m³/h by a control valve at the receiving terminal.
Where is the pressure highest, which sets the pipe rating? Where is it lowest, which decides whether the second station has suction pressure and whether the line stays full over the ridge? And how does that change with the flow?
5.3 Model schematic#

5.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Gasoline at 20 °C | Fluid library: 719 kg/m³, 0.58 cP |
| Units | m³/h, barg, m | Unit set of the project |
| T-101, sending tank | Open; base at 20.00 m, level 10.00 m | |
| T-201, receiving tank | Open; base at 85.00 m, level 12.00 m | |
| Line | 12 inch STD, 8 lengths of 6000 m; 50 m suction line | Commercial steel |
| Elevations, km 0 to 48 | 20, 35, 8, 55, 95, 205, 160, 120, 85 m | Route survey, every 6 km (assumed) |
| PS-1 | Rating mode; 252 m at 400 m³/h | Shut-off 300 m |
| PS-2, at km 24 | Rating mode; 184 m at 400 m³/h | Shut-off 232 m |
| FCV-B | Control target Flowrate, 400.00 m³/h | Second file: control target None, 100 % open |
| Station and terminal piping | 2 x open gate valve, 4 x 90° long radius elbow on L-4 and L-8 | From the fittings library |
5.5 Model set-up#




Each node carries the ground elevation at its kilometre post. That is all the model needs to account for the static head: a pipe's rise is the difference between its two nodes.
5.6 Calculation procedure#
- Open 05_Gasoline Pipeline.flmx and press Run.
- Press Graphs on the Tools page. The file holds one graph of type Path; press Generate.
- To build a path graph from nothing: Add Graph, leave Graph type at Path and the x axis at Length; press Add y axis var and choose Pressure and Elevation (Figure 65); press Add path items and choose the links of the route in order from the upstream end (Figure 66); then Generate. Extend opens the chart in a window of its own.
- Press Calculator to see the pumping power and energy.


5.7 Reference results#



5.8 Interpretation#
The highest pressure in the line is 18.45 barg at the discharge of the first station, and that is what the pipe and flange rating has to cover. It is not at the lowest point of the route: the river crossing sees less, because friction has already taken its share by then.
The lowest pressures are the two the profile is drawn to find. At the suction of the second station there are 3.42 barg, which is what that pump has for NPSH (61.23 m available). At the top of the ridge there are 6.20 barg, so the line is full and under pressure at its highest point. Both are held up by the control valve at the far end, which is taking 6.51 bar at 38 per cent open.
The two stations absorb 435.93 kW between them, or 1090 kWh for every thousand cubic metres delivered.
5.9 What-if investigation#
The throughput is varied from 300 to 430 m³/h in a scenario of type Sets whose one input is the set point of FCV-B. Its outputs are the three pressures that matter, the state of the valve, and the two calculations - a Calculator result can be chosen as a scenario output like any other.


5.10 Comparison#
As the flow rises the friction rises with it and every pressure downstream of a station falls: the suction of the second station goes from 9.02 barg at 300 m³/h to 1.44 barg at 430, and the ridge from 14.31 to 3.34 barg. The valve has 2.56 bar left at 430 m³/h. The energy per thousand cubic metres falls from 1265 to 1057 kWh, because at low flow more of the pump head is being destroyed in the valve.
The second file is the limit: the terminal valve left wide open. The line then finds its own flow, 440.25 m³/h, and that is the most these two stations can move. The second station is left with 0.74 barg of suction pressure and the ridge with 2.33 barg.


5.11 Engineering remarks#
- A path graph plots each pipe from its upstream to its downstream node. Put the links in in the order the liquid meets them; an element that is not a pipe adds no length.
- The pressure over a summit must stay above the vapour pressure of the product with margin or the column separates. Gasoline at 20 °C has a vapour pressure well below atmospheric here, so positive gauge pressure at the ridge is the practical test.
- A steady-state model says nothing about surge when the terminal valve closes or a station trips; that is a transient calculation.
- The elevations are every six kilometres. A real profile needs every high and low point of the survey, because a summit between two posts is not seen.
5.12 Exercise#
More throughput is wanted, and both stations can be fitted with larger impellers, which is close to running them faster. In 05_Gasoline Pipeline - terminal valve open.flmx add a scenario of type Sets with the Relative speed of PS-1 and of PS-2 as inputs and three cases - 1.00, 1.05 and 1.10 for both - and with the flow of PS-1, the pressure at KP0 and the pressure at KP30 as outputs. How much flow does ten per cent of speed buy, and what does it do to the highest pressure in the line?
Example 6 Fire water ring main#
Project file 06_Fire Water Ring Main.flmx
6.1 Objective#
To model a looped fire water main with a duty and a standby pump, to hold its fire cases in one file as a scenario and look at any of them on the sheet, and to find what the ring can deliver. The example uses the Darcy-Weisbach friction model; Example 7 uses Hazen-Williams.
6.2 Engineering problem#
A 10 inch ring 1300 m round is fed at one point from a fire water tank through a duty pump with a standby beside it. It has seven take-offs: four hydrants, two monitors and the deluge valve of a tank farm at the far corner. The fire water demand depends on where the fire is.
Does the ring deliver the design fire at the pressure the equipment needs? What is lost when one side of the ring is shut for maintenance on the day of the fire? And how much more than the design demand could the deluge valve take?
6.3 Model schematic#

6.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water at 25 °C | Fluid library |
| Units | m³/h, barg, m | Unit set of the project |
| Friction model | Darcy-Weisbach | Setting, Advanced |
| T-FW, fire water tank | Open; base at grade, level 10.00 m | |
| P-FW-A, duty pump | Rating mode; 105 m at 681 m³/h | Shut-off 126 m; 70 m at 1022 m³/h |
| P-FW-B, standby | The same pump, Pump on = No | |
| Ring main RM-1 to RM-8 | 10 inch schedule 40; 125 to 200 m per side | |
| Feed and suction | 12 inch; discharge 10 inch | |
| Laterals | 15 m; 6 inch, 8 inch to the deluge valve | |
| Demands | Hydrant 57, monitor 114, deluge valve 340 m³/h | Assumed design basis |
| Pipes | Fittings |
|---|---|
| Pump suctions S-A, S-B | 1 x open gate valve, 1 x 90° long radius elbow |
| Pump discharges D-A, D-B | 1 x swing check valve, 1 x open gate valve, 1 x 90° standard elbow |
| Feed to the ring | 2 x 90° standard elbow, 1 x branching tee |
| Ring corners RM-1, RM-3, RM-5, RM-8 | 1 x 90° standard elbow, 1 x open gate valve |
| Ring sides RM-2, RM-7 | 1 x open gate valve |
| Every lateral | 1 x branching tee, 1 x open gate valve |
| Case | Fire | H1 | H2 | M1 | M2 | DV1 | H3 | H4 | Ring |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Two hydrants | 57 | 57 | whole | |||||
| 2 | Process unit | 57 | 114 | 114 | 57 | whole | |||
| 3 | Tank farm (design) | 57 | 114 | 114 | 340 | 57 | whole | ||
| 4 | Tank farm | 57 | 114 | 114 | 340 | 57 | east side RM-7 closed | ||
| 5 | Tank farm | 57 | 114 | 114 | 340 | 57 | west side RM-2 closed |
6.5 Model set-up#






A pipe has a Status. Normal carries flow; Closed takes it out of the calculation without removing it from the drawing, which is how a shut sectional valve is modelled.

6.6 Calculation procedure#
- Open 06_Fire Water Ring Main.flmx and press Run. The base case is the design fire.
- Press Scenario on the Tools page to see how the five cases are set up (Figure 84). The inputs are the Flow In of the seven take-offs and the Status of RM-7 and RM-2; a status is typed as Normal or Closed.
- Close the Scenario Manager. On the Home page choose a case in the case selector; the sheet, the tables on it and the table of the selected element all show that case.
- Set the selector back to Base Scenario before changing anything.

6.7 Reference results#




6.8 Interpretation#
In the design fire the duty pump delivers 682.00 m³/h at 104.84 m, close to its rated point. The ring splits it: 329 m³/h goes west about and 353 east about. The deluge valve, the furthest take-off and the largest, has 10.19 barg. The Calculator holds the lowest pressure at any take-off, 10.19 barg, so the question whether every take-off has its pressure is answered by one number in every case.

6.9 What-if investigation#
Choose Case-4 in the case selector. The east side of the ring is shut, and everything for the tank farm has to go the long way round.




6.10 Comparison#
From the Results table: with the whole ring the deluge valve has 10.19 barg; with the east side shut 8.10 barg, and with the west side shut 8.90 barg. The pump is doing exactly the same in all three - the demands are fixed - so the 2.09 bar is what the second path round the ring is worth. The lowest take-off pressure falls from 10.19 to 8.10 barg. In the two smaller fires the pump runs back up its curve and every take-off has more than 12 barg.
How much could the deluge valve take? An Adjust in the same file varies the Flow In of DV1 until the pressure at DV1 falls to 7.00 barg, taken here as the least the deluge system needs at its inlet.

The answer is 585 m³/h against the design demand of 340: with the other design demands running, the ring and the pump have that much in hand for the tank farm.
6.11 Engineering remarks#
- A demand node takes its flow whatever the pressure. That is right for sizing the supply to a stated demand; it does not tell you what an open hydrant would actually pass at the pressure available. For that, model the outlet with a spray nozzle and its K factor, as in Example 7.
- A looped network has no unique direction for some pipes. Draw each one the way the water is expected to go in the design case; a negative flow then means it has turned round, as RM-6 does in Case-4.
- The standby pump is in the model so that changing over is one field. Running both is the exercise below, and pumps in parallel are the subject of Example 9.
- The minimum pressures here are assumptions. Take the real ones from the hydrant, monitor and deluge system data sheets and from the project's fire protection design basis.
6.12 Exercise#
Add a sixth case to the scenario: the design fire with both pumps running. Add the Pump status of P-FW-B to the inputs - it is typed ON or OFF - press Add case for the sixth, type OFF for the first five cases and ON for the sixth, and run. By how much does the pressure at DV1 rise, and what flow does each pump now deliver?
Example 7 Spray systems on two tanks#
Project files 07a_Spray - cylindrical tank.flmx 07b_Spray - rectangular tank, tree.flmx 07b_Spray - rectangular tank, grid.flmx
7.1 Objective#
To lay out, build and prove a water spray system with the Nozzle Layout tool: describe the tank, let Auto layout choose the nozzles, Insert the nozzles and their sized pipework into the model, run it, and use Adjust to find the supply pressure at which the worst nozzle has exactly what it needs. The example is calculated with the Hazen-Williams friction model.
7.2 Engineering problem#
Two tanks are to be given water spray cooling at 10.2 L/min for every square metre of exposed surface. One is a vertical cylindrical tank 5 m in diameter and 6 m high, to be ringed. The other is the flat roof of a rectangular tank, 10 m by 4 m, to be covered from above; its pipework can be run as a tree, with a main along the middle and a short branch to each nozzle either side of it, or as a grid, with a main along one edge and one branch line carrying each row of nozzles.
How many nozzles, where, on what pipe, and what must the fire water supply deliver at the foot of each system?
7.3 Model schematic#



7.4 Input data#
| Item | Cylindrical tank | Rectangular roof |
|---|---|---|
| Fluid | Water at 25 °C | Water at 25 °C |
| Units | L/min, barg, m | L/min, barg, m |
| Friction model | Hazen-Williams, C = 120 | Hazen-Williams, C = 120 |
| Surface | 5.00 m diameter, 6.00 m high | 10.00 m by 4.00 m |
| Duty | 10.2 L/min/m² of shell | 10.2 L/min/m² |
| Nozzle | K = 41 L/min/√bar | K = 26 L/min/√bar, 120° cone, 1.00 m standoff |
| Pipe | Schedule 40 steel, sized for 3 m/s | Schedule 40 steel, sized for 3 m/s |
| Supply | A known pressure at grade, to be found | A known pressure at grade, to be found |
Design basis The density of 10.2 L/min/m² and the limits in Figure 98 are the figures the tool is seeded with, taken from NFPA 15. They are the basis assumed for this example; confirm every one against the edition and the project specification that apply.
7.5 Model set-up#
The friction model. Fire water spray systems are calculated with Hazen-Williams. Press Setting on the Tools page, choose Advanced, and under Pressure drop model select Hazen Williams. Pipes then carry a C coefficient instead of a roughness, and their fittings are held as equivalent lengths instead of K factors.

The arrangement. Press Nozzle Layout on the Tools page. Choose the Shape type, describe the tank and the nozzle, and press Auto layout: the tool finds the fewest nozzles that satisfy every rule and reports what each will pass and at what pressure.

For the cylinder Auto layout gives 2 rings of 6 nozzles, 12 in all, each passing 80.11 L/min at 3.818 barg, 961.3 L/min in total. The rings are 3.000 m apart and the nozzles 2.618 m apart round the shell.


For the roof Auto layout gives 4 columns by 2 rows, 8 nozzles each passing 51.00 L/min at 3.848 barg. Each wets a circle 3.464 m across; the nozzles are 2.449 m apart and the circles overlap by 29.29 per cent.
7.6 Calculation procedure#
- Start a new project, set the units and choose Hazen Williams as above.
- Open Nozzle Layout, fill in the tank and the nozzle from Table 16 and press Auto layout.
- Press Insert. The Insert dialog asks how the pipework is to be built (Figure 100): leave Size the pipework as it is inserted ticked, choose the schedule and the maximum velocity, and for a ring tick All rings the same size. Press Insert in the dialog.
- Click on the flowsheet where the system is to stand. The nozzles, the pipes, their lengths, elevations, sizes and fittings are all created, with a supply node at grade given a first pressure.
- Press Run.


What Insert builds is ordinary model. Every nozzle is a spray nozzle element with its K factor, its required flow and its minimum pressure; every pipe has a schedule size and a C coefficient; and each pipe where the flow turns - at an elbow, or into a branch at a tee - carries that fitting as an equivalent length from the NFPA table.



7.7 Reference results#



As inserted, the supply node N20 holds 4.90 barg - the nozzle pressure plus the static lift to the top of the tank plus a margin of half a bar - and the system takes 1021 L/min against the 961.3 required. Every nozzle is over its required flow; the least is 4.4 per cent over. The insert chose 16 x 2 in, 3 x 3 in, 2 x 4 in pipe.
7.8 Interpretation#
A ring is fed at one point and the water goes both ways round, so the nozzle opposite the feed is reached by two half-rings instead of one whole one. That is why a 2 inch ring is enough and why the six nozzle pressures of Figure 107 differ by only 25 mbar. The larger difference is between the rings: the top ring stands three metres above the lower one, and its nozzles have about 0.29 bar less. The worst nozzle is therefore on the top ring, and it is Nz3.
Overdesign is how far a nozzle's flow is above its required flow. A positive figure on every nozzle means the supply pressure is more than the system needs; the question is how much more.
7.9 What-if investigation#
The supply pressure the system needs is the one at which the worst nozzle is exactly at its minimum pressure of 3.82 barg. Adjust finds it: the adjusted variable is the Pressure of the supply node N20, the target is the Pressure of nozzle Nz3, and the target value is 3.82.

The answer is 4.55 barg at grade, at which the system takes 980 L/min. Press Apply Solution to write it into the supply node. These two numbers - a flow and the pressure it is wanted at - are the demand this spray system places on the fire water main, and are what a take-off of Example 6 stands for.
7.10 Comparison#
The rectangular roof is inserted twice from the same arrangement, once as a tree and once as a grid, and each is adjusted in the same way.






| Cylinder, rings | Roof, tree | Roof, grid | |
|---|---|---|---|
| Nozzles | 12 | 8 | 8 |
| Pipe chosen by the insert | 16 x 2 in, 3 x 3 in, 2 x 4 in | 8 x 0.75 in, 2 x 1.5 in, 1 x 2 in, 1 x 3 in | 2 x 0.75 in, 8 x 1.5 in, 1 x 3 in |
| Supply pressure as inserted (barg) | 4.90 | 4.45 | 4.45 |
| Flow as inserted (L/min) | 1021.49 | 420.17 | 424.88 |
| Least overdesign as inserted (%) | 4.37 | 1.73 | 2.28 |
| Worst nozzle | Nz3 | Nz7 | Nz8 |
| Supply pressure needed, by Adjust (barg) | 4.55 | 4.30 | 4.26 |
| Flow at that pressure (L/min) | 980.20 | 413.00 | 415.44 |
The grid needs 0.04 bar less at the supply than the tree for the same eight nozzles. It is not free: the insert gives the grid larger branch pipe, because each branch now carries four nozzles instead of one. The comparison a designer makes is that pressure against that pipe.
7.11 Engineering remarks#
- The sizing done by Insert is preliminary: the smallest size in the schedule that holds the velocity limit. It is a starting point. Change any pipe in its own window and run again, or use the Sizing tool of Example 4.
- In a Hazen-Williams project a fitting is an equivalent length taken from the NFPA table for the pipe's size and corrected for its C. Flow straight through a tee has no equivalent length; an elbow and a tee where the flow turns do. This is why the pipe that brings water into a ring carries a tee and the runs between nozzles carry nothing.
- A spray nozzle is modelled by its K factor: flow equals K times the square root of the pressure at it. Its required flow and minimum pressure are what Overdesign and the warnings are judged against.
- The supply is a node with a known pressure. Tick Auto Adjust in the Adjust window and every Run finds that pressure again, which keeps it right while pipe sizes are being changed.
- The velocity rule knows nothing of a minimum pipe size. For the small nozzles of the roof it chooses 0.75 inch branches; where the standard or the specification sets a minimum size for spray pipework, raise them to it and run again.
- The arrangement is kept with the project. Open Nozzle Layout again to see what the system was laid out from.
7.12 Exercise#
The 2 inch rings are to be tried at 1.5 inch to save pipe. Open 07a_Spray - cylindrical tank.flmx, press Apply Solution in Adjust so that the supply is at 4.55 barg, then change the ring pipes of the top ring to 1.5 inch and run. Which nozzle is now the worst, and by how much is it under its required flow? Use Adjust again to find the new supply pressure, and decide whether the smaller pipe is worth it.
Example 8 LNG rundown line#
Project file 08_LNG Rundown Line.flmx
8.1 Objective#
To model a cryogenic rundown line with a fluid and a pipe material taken from the libraries, to follow the pressure along it with a path graph, and to keep in a Calculator the one number that decides whether the design works: how far the liquid is above its bubble point when it reaches the last valve.
8.2 Engineering problem#
LNG leaves the product drum of a liquefaction train at its bubble point. A rundown pump sends it through 1.5 km of 16 inch stainless steel line on a pipe rack and up the side of a storage tank to its roof, 42 m above grade, where a flow control valve lets it down into the tank's vapour space.
Anywhere the pressure in the line falls to the vapour pressure the liquid flashes. The lowest pressure is at the top of the tank, just before the valve: the pump's head has been spent on friction and on 41 m of lift. Is there margin there, and how much rundown can the line take before it is gone?
8.3 Model schematic#

8.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | LNG at -158 °C | Fluid library: 450.00 kg/m³, 0.14 cP, vapour pressure 0.25 barg |
| Units | m³/h, barg, m | Unit set of the project |
| V-1601, product drum | 0.25 barg; base at 5.00 m, level 2.00 m | At the bubble point of the liquid |
| P-1601 | Rating mode; 74.5 m at 1250 m³/h | Shut-off 96 m; best efficiency 80 % |
| L-1, suction | 15 m of 20 inch schedule 10S | 1 x open gate valve, 2 x 90° long radius elbow |
| L-2, up to the rack | 30 m of 16 inch schedule 10S | 1 x swing check valve, 1 x open gate valve, 2 x 90° long radius elbow |
| L-3 to L-5, on the rack at 8 m | 500, 500 and 440 m | 10 x 90° long radius elbow each: expansion loops |
| L-6, down from the rack | 30 m | 2 x 90° long radius elbow |
| L-7, up the tank to 42 m | 42 m | 3 x 90° long radius elbow, 1 x open gate valve |
| Pipe material | Stainless Steel | Material library: roughness 0.015 mm |
| FCV-1 | Control target Flowrate, 1250.00 m³/h | |
| Tank vapour space | 0.15 barg at 42 m | Known pressure at the outlet |
Library data The LNG properties in the fluid library are for a typical lean LNG and are tabulated from -165 to -150 °C. A real rundown must be calculated with the properties of the actual composition; type them in Fluid Properties, or add the composition as a new fluid in the Database.
8.5 Model set-up#






8.6 Calculation procedure#
- Open 08_LNG Rundown Line.flmx and press Run.
- Press Graphs and Generate for the pressure and elevation along the line.
- Press Calculator. The first calculation is the pressure at N9, the inlet of the valve, less 0.25, the bubble point pressure in barg.
- Press Scenario for the rundown rates of section 8.9.
8.7 Reference results#



8.8 Interpretation#
The pump delivers 1250 m³/h at 74.48 m for 142.70 kW. The pressure at its discharge is 3.79 barg; 0.89 barg is left at N9 on the tank roof, 0.64 bar above the bubble point. Of what was lost on the way, the climb up the side of the tank, from N8 to N9, took 1.86 bar, almost all of it static head: a liquid of 450 kg/m³ loses only 0.44 bar for every ten metres, but the roof is 41 m above the pump.
The valve takes 0.73 bar at 32 per cent open, and it is deliberately the last thing in the line: the liquid is kept above its bubble point all the way up, and flashes only across the valve, into the tank.
The NPSH available at the pump is 5.78 m. A liquid at its bubble point has no NPSH of its own; all of it is the liquid level in the drum above the pump, less the loss in the suction line.
8.9 What-if investigation#
The rundown rate is varied from 1000 to 1375 m³/h in a scenario of type Sets on the set point of FCV-1. The margin from the Calculator is one of its outputs.


8.10 Comparison#
The margin over the bubble point is 1.37 bar at 1000 m³/h, 0.64 bar at 1250 and 0.21 bar at 1375. It falls quickly because two things happen together as the flow rises: the pump gives less head, 69.95 m at 1375 against 82.24 m at 1000, and the line takes more. At 1375 m³/h the valve is 54 per cent open with 0.30 bar across it: the line is close to the most it can pass, and close to flashing at the roof.

8.11 Engineering remarks#
- The model is single-phase. It is right for as long as the calculated pressure stays above the bubble point everywhere, and the Calculator is how that is watched; below it the real line carries two phases and the result no longer applies.
- Heat leak warms the liquid along the line and raises its bubble point. The model is isothermal, so the margin it reports is the margin at the drum temperature; a real design takes the warming off the margin.
- Running the fluid colder in the library - Fluid Properties, -160 °C - is the quick way to see what subcooling is worth: the vapour pressure falls and the margin grows by the same amount.
- Fittings from the library are K factors for ordinary service. Cryogenic valves and expansion loops should be confirmed against vendor data.
8.12 Exercise#
The rundown is to be raised to 1500 m³/h. Show that the present line cannot do it: set the selector to Base Scenario, set FCV-1 to control target None and 100 per cent open, run, and read the flow. Then change the three rack lengths L-3, L-4 and L-5 to 18 inch schedule 10S and run again. What flow does the line now pass wide open, and what is the margin over the bubble point at 1500 m³/h with the valve controlling?
Example 9 Three pumps in parallel, and an NPSH problem#
Project files 09_Parallel Pumps.flmx 09_Parallel Pumps - one pump, suction study.flmx 09_Parallel Pumps - 16 in suction.flmx
9.1 Objective#
To run a station of three pumps in parallel with one, two and three in service as a scenario, to see why the flow does not add up, and to find and cure the NPSH problem that appears when one pump runs alone. The example introduces the NPSH required curve of a pump, the warnings list, and a scenario on a pipe size.
9.2 Engineering problem#
A cooling water station has three identical pumps, each rated 600 m³/h at 42 m, drawing from a basin through a common suction header and discharging through non-return valves into a 900 m, 16 inch main to a cooling tower deck. Two pumps carry the normal duty and the third is the spare. The pumps stand a metre and a half above the basin water, and their suction lines are 10 inch.
The station has run for years on two pumps. During an outage one pump is run alone to keep part of the plant cooled, and it is noisy and its discharge pressure flickers: the signs of cavitation. Why does a pump that is content beside another object to running alone, and what is to be done about it?
9.3 Model schematic#

9.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water at 30 °C | Fluid library: vapour pressure 0.042 bar absolute |
| Units | m³/h, barg, m | Unit set of the project |
| BASIN | Open; floor at grade, level 3.00 m | |
| DECK, cooling tower | Open; floor at 14.00 m, level 1.00 m | Static lift 12 m |
| P-A, P-B, P-C | Rating mode; 42.0 m at 600 m³/h; pumps at 4.50 m | Curve and NPSH required: the pump curve data in section 9.5 |
| SH, suction header | 12 m of 20 inch | 2 x 90° long radius elbow |
| PS-A to PS-C, suction lines | 6 m of 10 inch schedule 40 | 1 x branching tee, 1 x open gate valve, 1 x 90° long radius elbow |
| NRV-A to NRV-C | Valve with No reverse flow | |
| PD-A to PD-C, discharge lines | 6 m of 10 inch | 1 x 90° standard elbow, 1 x open gate valve, 1 x branching tee |
| M-1, M-2, the main | 450 m of 16 inch each | 4 x 90° standard elbow each |
| PLANT | PD, 1.20 bar at 1200 m³/h | The exchangers, lumped |
9.5 Model set-up#

A pump's curve is typed point by point: press Enter data in the pump window. The fourth column is the NPSH the pump requires at each flow, from the maker's curve. With it entered FlowMax compares the NPSH available with the NPSH required at the flow the pump is running at.





9.6 Calculation procedure#
- Open 09_Parallel Pumps.flmx and press Run. Two pumps are on in the base case.
- Press Scenario on the Tools page. The inputs are the Pump status of P-B and P-C, typed ON or OFF; the three cases are one, two and three pumps running.
- Close it and choose Case-1, one pump alone, in the case selector on the Home page.
- Press Graphs for P-A against the system it shares.
- Open 09_Parallel Pumps - one pump, suction study.flmx, in which one pump alone is the base case, and press Run. The message that ends the run offers Warnings / Errors; press itto open the list.
9.7 Reference results#





9.8 Interpretation#
Two pumps deliver 1166 m³/h between them, 583 each. Three deliver 1297, not half as much again: every extra pump pushes the main further up its square-law resistance, so each one is pushed back along its curve to 432 m³/h. One pump alone does the opposite. With the main almost empty of friction it runs out to 819 m³/h, 36 per cent beyond its rated flow, at only 31.69 m.
The energy to move a thousand cubic metres is 114, 143 and 180 kWh with one, two and three pumps: the more water is pushed through the same main, the more each cubic metre costs.
9.9 What-if investigation#
Now the NPSH. The NPSH available to P-A is in the scenario table: 7.63 m with three running, 7.22 m with two and 6.35 m alone. It falls because the suction line carries more flow and loses more. At the same time the pump needs more: from the curve of Figure 130 the NPSH required is 3.34 m at 432 m³/h, 4.11 m at 583 and 6.88 m at 819. Alone, the pump has 6.35 m and needs 6.88 m. It is 0.53 m short, and it cavitates.



Three things could cure it: more water over the pump, a pump that needs less, or less loss in the suction line. The first two are civil work and a new pump. The third is a pipe, and the velocity in Figure 140 says it is the right place to look: 4.47 m/s is far too fast for a suction line. The second file studies it with a scenario whose one input is the Inside diameter of PS-A, for the schedule 40 sizes 10, 12, 14 and 16 inch.


9.10 Comparison#
| Suction line | Flow (m³/h) | Velocity (m/s) | NPSHa (m) | NPSHr at that flow (m) | Margin (m) |
|---|---|---|---|---|---|
| 10 inch | 818.50 | 4.47 | 6.35 | 6.88 | -0.53 |
| 12 inch | 828.80 | 3.19 | 7.35 | 7.07 | 0.28 |
| 14 inch | 832.00 | 2.65 | 7.67 | 7.13 | 0.54 |
| 16 inch | 834.80 | 2.03 | 7.95 | 7.18 | 0.77 |
A larger suction line gives the pump more NPSH and, because it also lets the pump run a little further out, asks slightly more of it. Twelve inch removes the deficit but leaves almost nothing in hand. Against a project rule of at least 0.6 m of margin, taken here as the criterion, 16 inch is the size that passes.
09_Parallel Pumps - 16 in suction.flmx is the station with all three suction lines changed to 16 inch, and the pump scenario run again.



One pump alone now has 7.95 m available at 835 m³/h against 7.18 m required, a margin of 0.77 m, and the run raises no warning. With two and three pumps the NPSH available is 8.04 and 8.08 m; the normal duty is hardly changed.

9.11 Engineering remarks#
- NPSH available is worked out by FlowMax at the pump's suction node from the pressure there, the velocity and the vapour pressure of the fluid. NPSH required comes only from the pump curve data; if the fourth column is left empty there is nothing to compare with and no warning can be given.
- The NPSH required on a maker's curve is usually the 3 per cent head drop figure. A pump running at exactly that is already cavitating; the margin is not optional.
- Run-out is the case to check, not the rated point. A pump in a parallel station sees its highest flow and lowest NPSH available when it is the only one running.
- A non-return valve behind a pump that is off is held shut by the pumps that are running. The pressure behind it is higher than in front of it and that is not a fault.
- The scenario on Inside diameter changes only the bore used in the calculation. To adopt a size, choose it in the pipe window so that the schedule, the nominal size and the outside diameter change with it.
9.12 Exercise#
Instead of changing the pipe, could the single pump simply be held back from running out? In 09_Parallel Pumps - one pump, suction study.flmx use Adjust with the Reference pressure drop of PLANT as the adjusted variable and the flow of P-A as the target, and find the plant resistance at which the pump is held to 700 m³/h. Then read the NPSH available and compare it with the NPSH required at 700 m³/h from Figure 130. Is throttling a cure, and what does it cost in cooling water?
Example 10 A warehouse sprinkler system, NFPA 13#
Project file 10_Sprinklers - warehouse, NFPA 13.flmx
10.1 Objective#
To calculate a wet pipe sprinkler system the way NFPA 13 sets the calculation out, on FlowMax's isometric sheet: the sprinklers as spray nozzles with their K factor, the pipe in Hazen-Williams, the tees and elbows drawn on the sheet carrying their NFPA equivalent lengths, Adjust to find the pressure the system needs where it is fed, and the NFPA calculation of the PDF report with its graph of the water supply against the demand.
10.2 Engineering problem#
A warehouse is to be protected by a wet pipe sprinkler system designed to NFPA 13 for Ordinary Hazard Group 2: a density of 8.1 mm/min (8.1 L/min for every square metre) over a design area of 139 m². The sprinklers are K80 pendents, 3.0 m apart on branch lines 4.0 m apart, so each covers 12 m² and must discharge at least 97.2 L/min. Twelve sprinklers make the design area, and NFPA 13 asks for it to be a rectangle 1.2√A = 14.1 m long along the branch lines: five sprinklers on each of two lines and two on a third, at the far end of the lines farthest from the riser.
The system is fed from the town main through 60 m of 6 in. cement-lined underground. A flow test at the connection gave 5.5 barg static and 4.0 barg residual with 3800 L/min flowing, and 950 L/min must be allowed for hose streams. What does the system need at the connection, and is the town main enough?
10.3 Model schematic#

10.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid | Water at 25 °C, 996.9 kg/m³ | |
| Units | L/min, barg, m | |
| Friction model | Hazen-Williams, C 120 (black steel, wet); C 140 underground (cement lined) | NFPA 13 |
| Hazard | Ordinary Hazard Group 2: 8.1 mm/min over 139 m² | NFPA 13 density/area curve |
| Sprinklers | K 80 L/min/√bar, 12 m² each, required 97.2 L/min, at least 0.5 bar | NFPA 13 |
| Branch lines | 13.5 m of 2-1/2 in. to the first open sprinkler, then 1-1/2, 1-1/2, 1-1/4 and 1 in.; 3 m apart; 8.5 m up | |
| Cross main | 4 in. for 32 m from the riser, then 3 in.; lines 4 m apart | |
| Riser | 4 in., 8.5 m, OS&Y gate valve and alarm check valve | Alarm valve taken as a swing check |
| Underground | 6 in., 60 m, post indicator valve | |
| Water supply test | 5.5 barg static, 4.0 barg residual at 3800 L/min | Town main flow test |
| Hose allowance | 950 L/min | NFPA 13, Ordinary Hazard |
Design basis The hazard, the density, the sprinkler and the water supply test are assumed for the example. On a project they come from the owner's hazard classification, the sprinkler's listing and a flow test witnessed at the connection.
10.5 Model set-up#
The friction model. Press Setting on the Home page, choose Advanced, and select Hazen Williams. Pipes then carry a C factor, and fittings are held as equivalent lengths of pipe, as NFPA 13 tabulates them. The box beside it, Velocity pressure, is left clear: NFPA 13 lets the calculation be made by total pressure alone (section 10.9 ticks it).

The isometric sheet. Right-click on an empty part of the sheet and choose Drawing mode, then Isometric. The grid becomes a lattice of lines at 30 degrees, and every node drawn lands on it: pipes run along the three axes of an isometric drawing - east down to the right, north up to the right, and up. The drawing mode is saved with the project. It changes how the model is drawn, not how it is calculated: lengths and elevations are typed, never measured off the sheet.
The sprinklers. Each is a Spray element from the Equipment strip, drawn from its branch line node to a tip node of its own that discharges to atmosphere. Its window takes the K factor, the required flow and the minimum pressure.

The pipes. In a Hazen-Williams project the pipe window offers a material from the C factor list and shows the pipe's equivalent length of fittings. The riser carries its two valves in its own list, from Details Fittings: the OS&Y gate valve and the alarm check valve, together 7.30 m of 4 in. pipe.


The tees and elbows. Where the water turns, an Elbow or a Tee from the Equipment strip is placed on the node. In a Hazen-Williams project its window shows its NFPA equivalent length instead of a K factor, and the solver adds that length to the pipe the water turns into: the elbow at the foot of the riser, the elbow at RT into the cross main (3.00 m of 4 in.), the tees at CM3 and CM2 into lines 3 and 2 (2.40 m of 1-1/2 in. and 3.70 m of 2-1/2 in.), and the elbow at CM1 into line 1 (1.80 m). The run through a tee is given nothing, which is NFPA 13's rule.


The connection to the town main is node CITY, given a pressure. Any first guess will do: section 10.6 finds the pressure the design area needs.
10.6 Calculation procedure#
- Set the units, Hazen Williams and the isometric drawing mode as above, and draw the model of Figure 149.
- Give CITY a first pressure, 3 barg, and press Run.
- Find the most remote sprinkler: the one with the least overdesign. Here it is SP2-10, at the end of branch line 2.
- Open Adjust on the Tools page. The adjusted variable is the Pressure of CITY, the target the Pressure of SP2-10, the target value 1.476 barg: the pressure at which a K80 sprinkler discharges 97.2 L/min. Press Start, then Apply Solution.
- On the Reports page press Report, tick NFPA 13 / 15 calculation, type the water supply test and the hose allowance (Figure 157) and press Generate report.


10.7 Reference results#


Adjust settles at 3.834 barg at the town main. The system then takes 1282 L/min, and with the hose allowance 2232 L/min. The most remote sprinkler, SP2-10, discharges 97.19 L/min at 1.476 barg; the first open sprinkler of the same line discharges 117.4 L/min, 21 per cent over its requirement, because it stands nearer the feed.


10.8 Interpretation#
The 2.36 bar between the town main and the most remote sprinkler is spent as follows: 0.97 bar along branch line 2 from the cross main, 0.36 bar in the cross main, 0.15 bar to friction in the riser and its valves, 0.83 bar to lift the water 8.5 m, and 0.05 bar in the underground. The branch line takes the most: small pipe, carrying the whole of its line's flow.
The supply curve gives 4.94 barg at 2232 L/min, against the 3.83 barg needed: a margin of 1.11 bar. The town main is enough. Many authorities ask for a margin, often 0.5 bar (about 10 psi); this one has it.
Line 2 and not line 1 holds the most remote sprinkler, although line 1 is farther along the cross main: water reaches line 2 through a tee, whose NFPA length (3.70 m) is about twice that of the elbow into line 1 (1.80 m), and that outweighs the extra 4 m of 3 in. cross main. The program finds it from the results; it is not assumed.
10.9 What-if investigation#
NFPA 13 allows the calculation to be made with the velocity pressure: a sprinkler with flow passing on beyond it discharges by its normal pressure, Pn = Pt - Pv, where Pv is the velocity pressure in the pipe feeding it; the last sprinkler of a line still discharges by Pt. Tick Velocity pressure in Setting, Advanced, and run Adjust again.
The town main then needs 3.792 barg and the system takes 1260 L/min, against 3.834 barg and 1282 L/min by total pressure. The first open sprinkler of line 2 now discharges 115.9 L/min instead of 117.4. Taking the velocity pressure in gives a slightly smaller demand, because the sprinklers nearer the feed are no longer credited with pressure that is moving the water past them; the total pressure method is the conservative and the usual one.
10.10 Comparison#
The calculation can be checked by hand as NFPA 13 sets it out, starting at the most remote sprinkler and working back towards the supply: its flow from K√P, the friction of each pipe from p = 6.05 x 10^5 Q^1.85 / (C^1.85 d^4.87) bar/m with Q in L/min and d in mm, and each sprinkler upstream discharging at the pressure that leaves at its node.
| Step | By hand | FlowMax |
|---|---|---|
| SP2-10 : flow at 1.476 barg | 97.20 L/min | 97.19 L/min |
| B2-5, 1 in. (26.64 mm), 3 m, 97.20 L/min : friction | 0.140 bar | 0.140 bar |
| Pressure at S2-9 | 1.616 barg | 1.616 barg |
| SP2-9 : flow | 101.71 L/min | 101.70 L/min |
| B2-4, 1-1/4 in. (35.05 mm), 3 m, 198.9 L/min : friction | 0.139 bar | 0.139 bar |
| Pressure at S2-8 | 1.755 barg | 1.755 barg |
| SP2-8 : flow | 105.99 L/min | 105.98 L/min |
| B2-3, 1-1/2 in. (40.89 mm), 3 m : friction | 0.144 bar | 0.144 bar |
| Pressure at S2-7 | 1.899 barg | 1.899 barg |
The two agree to the third decimal: the program's Hazen-Williams is NFPA's. The report's pipe table (Figure 160) is the same calculation for every pipe, with the fittings' equivalent length Le added to the length: Pf = p x (L + Le).
10.11 Engineering remarks#
- Only the sprinklers of the design area are drawn. That is NFPA 13's method - the sprinklers outside it are assumed shut - and it keeps the model within a Lite licence. The pipe to the first open sprinkler carries the run past the shut ones, with no tees counted for them.
- The most remote area is not always the farthest one. A calculation is normally made for the area NFPA 13 points to and checked for any other that could need more: an area beside the riser on smaller pipe, a high bay.
- The alarm check valve is taken here as a swing check of the NFPA table. On a project its listed friction loss, from the manufacturer, is used instead.
- A dry pipe or preaction system is calculated with C 100 for black steel; the same model with the material changed answers it. NFPA 13 also limits the time a dry system takes to deliver water, which this calculation does not cover.
- The equivalent lengths of fittings are NFPA 13's for schedule 40 at C 120, corrected for the actual bore and C as the standard says.
10.12 Exercise#
Replace the twelve K80 sprinklers with K115 (K 8.0 in US units) and keep the density. What pressure does the most remote sprinkler need now, what does the town main have to give, and how much margin is left? Then change the pipe material to Black Steel (Dry Systems) for a dry pipe system and repeat.
Example 11 Deluge water spray on a horizontal drum, NFPA 15#
Project files 11_Deluge - horizontal drum, NFPA 15.flmx 11_Deluge - horizontal drum, restriction orifice.flmx
11.1 Objective#
To calculate a deluge water spray system to NFPA 15 drawn by hand on the isometric sheet: open nozzles on three headers round a vessel, the deluge valve outside the fire zone, fittings as equivalent lengths in each pipe's own list, Adjust to find the pressure the system needs where it leaves the fire main, and a restriction orifice - a PD element in its Orifice model, ISO 5167-2 - to suit the system to the higher pressure the main actually gives.
11.2 Engineering problem#
A horizontal drum, 3.0 m in diameter and 10.0 m long, its axis 4.0 m above grade, is to be given water spray exposure protection at 10.2 L/min/m² over its shell and heads: 108.4 m², 1106 L/min. Twelve K57 nozzles on three headers - two above the drum, north and south, one beneath it, four nozzles 2.5 m apart on each - must each discharge 92.1 L/min. The deluge valve stands at grade 15 m away, outside the fire zone, and the pipe beyond it is dry until it opens.
What pressure does the system need where it leaves the fire main, and what happens when the main, in the fire case of the plant, gives 7.0 barg there?
11.3 Model schematic#

11.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid, units, friction | Water at 25 °C; L/min, barg, m; Hazen-Williams | |
| Pipe | Black steel (wet) C 120 to the deluge valve; galvanized C 120 beyond it | NFPA 15 |
| Drum | 3.0 m x 10.0 m, axis 4.0 m up, shell and heads 108.4 m² | |
| Density | 10.2 L/min/m², 1106 L/min in all | NFPA 15, exposure protection |
| Nozzles | 12 x K 57 L/min/√bar, 92.1 L/min each, at least 1.4 bar | NFPA 15 |
| Headers | Upper two at 5.6 m, bottom one at 2.0 m; 2, 1-1/2, 1-1/4, 1 in. | |
| Deluge valve | 4 in., Cv 200 | Assumed; the valve's listed loss on a project |
| Fire main at the take-off | 7.0 barg in the fire case | From the ring main calculation, {sec:e6} |
11.5 Model set-up#
The project is set up as section 10.5: Hazen Williams, the isometric drawing mode, nozzles from the Spray element. The nozzles on the upper headers point down at the drum and those on the bottom header up; on the sheet only the direction of the tip differs.


Fittings in each pipe's own list. Example 10 put its tees and elbows on the sheet; here each pipe lists the fittings the water turns through on its way in, from Details Fittings in the pipe window: the tee off the main and the gate valve on TO-1, the elbow at the foot of the riser on R-1 (3.00 m), the tee into the bottom header on B-1 (3.00 m), the tee at M on H-N and H-S (3.00 m each), and the elbow into each upper header on N-1 and S-1 (1.50 m). Both ways give the same result; the list is the quicker where several fittings fall on one pipe, the sheet the clearer to read.

11.6 Calculation procedure#
- Draw the model of Figure 162 and give TO a first pressure, 5 barg.
- Press Run and find the nozzle with the least overdesign: SN-N4, at the far end of the south header.
- Open Adjust: adjusted variable the Pressure of TO, target the Pressure of SN-N4, target value 2.612 barg - the pressure at which K 57 gives 92.1 L/min, above NFPA 15's 1.4 bar. Press Start, then Apply Solution.
- Give TO the main's 7.0 barg and run again to see what the system would take.
- Open the second file: the spool beyond the deluge valve is replaced by RO-1, a PD element drawn as a flow element, in its Orifice model (Figure 170). Try bores until the most remote nozzle is just above its flow.

11.7 Reference results#


The system needs 4.00 barg at the take-off and then takes 1166 L/min, 5.5 per cent more than the 1106 L/min of the design density: the nozzles nearer the feed discharge more than they need. They range from 92.1 to 104.6 L/min. The deluge valve takes 0.16 bar.

11.8 Interpretation#
The most remote nozzle is at the far end of an upper header, 5.6 m up and farthest along the pipe. The bottom header, 3.6 m lower, has the lift on its side: its first nozzle gives 104.6 L/min against 92.1 at the end of the upper header. A deluge system cannot be balanced by its nozzles alone; it is sized so that the worst is right and the others are over.
At the main's 7.0 barg the same system would take 1581 L/min, 43 per cent over the design flow, the most remote nozzle giving 126.2 L/min. Water the plant's fire case did not count on is then drawn from the main, and the other users on it are left with less.
11.9 What-if investigation#
A restriction orifice beyond the deluge valve takes the pressure the system does not need. In the second file the spool is replaced by RO-1, a PD element whose Orifice model works out its loss by ISO 5167-2 from its bore, the bore of the pipe at its inlet and the pressure taps.

With the main at 7.0 barg, a bore of 40 mm in the 102.3 mm pipe (β 0.391) leaves the most remote nozzle SN-S4 with 94.5 L/min, and the system takes 1195 L/min. The orifice takes 2.82 bar.


11.10 Comparison#
The orifice's loss can be checked by hand from ISO 5167-2. The flow gives the differential pressure across the plate, Δp = ρ/2 (q √(1-β⁴) / (C π d²/4))², and the pressure lost to the line is the part of it not recovered downstream, Δϖ = Δp (√(1-β⁴(1-C²)) - Cβ²) / (√(1-β⁴(1-C²)) + Cβ²).
| Quantity | By hand | FlowMax |
|---|---|---|
| Flow | 1195 L/min | 1195 L/min |
| β = d / D | 0.391 | 0.391 |
| Discharge coefficient C | 0.600 | |
| Differential pressure Δp | 3.395 bar | |
| Pressure loss Δϖ | 2.820 bar | 2.820 bar |
| Most remote nozzle SN-S4 : K √P | 94.5 L/min | 94.5 L/min |
11.11 Engineering remarks#
- The pressure the main gives at a take-off depends on what else is flowing. The orifice is sized for the main's pressure in the fire case the system belongs to; if another case gives more, the system takes more then, and the main is checked for it.
- An orifice that is too small starves the system when the main is weak. The bore is rounded up, never down, and the system is checked at the lowest pressure the main can have.
- NFPA 15 asks for the nozzles to be listed and for their minimum pressure to be kept; the pressure that gives the required flow is usually the one that governs, as here.
- Downstream of the deluge valve the pipe is dry until the valve opens; how long the water takes to reach the last nozzle is a transient question - the Transient Training Manual fills a dry deluge.
11.12 Exercise#
Remove the bottom header's last nozzle and spread the duty over eleven nozzles (K 61). Find the pressure the system needs, the flow at the main's 7.0 barg, and the bore of the orifice that suits it.
Example 12 A fire pump and two standpipes, NFPA 20 and NFPA 14#
Project file 12_Fire pump and standpipes, NFPA 20 and 14.flmx
12.1 Objective#
To check a fire pump against NFPA 20's acceptance points and a standpipe system against NFPA 14's demand with one model: the pump on its curve, the cases of the flow test and the fire as a Sets scenario, the pump's net pressure as a Calculator formula, a pressure-reducing valve on the lowest hose valve, and Adjust to find how much the pump may wear before the top outlet is short.
12.2 Engineering problem#
An office building of eight storeys has two Class I standpipes, A and B, 6 in., one in each stair, with a 2-1/2 in. hose valve 1.2 m above each landing; the highest is 29.2 m up. NFPA 14 asks for 946 L/min (250 gpm) at each of the two highest outlets of the most remote standpipe and at the highest outlet of the other, with 6.9 bar (100 psi) left at the most remote, and no hose outlet above 12.1 bar (175 psi).
An electric fire pump rated 2839 L/min (750 gpm) at 10.3 bar (150 psi) draws from a tank at grade and has its test header outside the pump room. Does the pump meet NFPA 20 - no more than 140 per cent of its rated pressure at churn, at least 65 per cent at 150 per cent of its rated flow - does it meet the standpipe demand, and what does the lowest hose valve see?
12.3 Model schematic#

12.4 Input data#
| Item | Value | Basis |
|---|---|---|
| Fluid, units, friction | Water at 25 °C; L/min, barg, m; Hazen-Williams, C 120 | NFPA 14 |
| Fire pump | Rated 2839 L/min at 10.3 bar (105.3 m); churn 120 %, 150 % flow at 68 % | Assumed curve meeting NFPA 20 |
| Tank | Water 3.0 m above its floor at grade | |
| Header | 6 in.: 25 m to standpipe B, 40 m more to A | |
| Standpipes | 6 in.; hose valves 1.2 m above each landing, 4 m apart; the highest 29.2 m up | |
| Demand | 946 L/min at A8, A7 and B8; 6.9 bar left at A8 | NFPA 14 |
| Hose outlets | No more than 12.1 bar; PRV-1 set at 6.9 bar | NFPA 14 |
12.5 Model set-up#
The pump is a Pump element on its curve, in Rating: the five points of Table 25 typed with Enter data. Its suction is the tank, a Tank element with its level; its discharge goes through a check valve and a gate valve, both in the fittings list of D-1.

The hose valves are nodes with a Flow In: 946 L/min leaving at A8, A7 and B8 as the file opens, and nothing at the test header. The pressure-reducing valve PRV-1 is a Valve with its Specification on Pressure set: it holds the pressure at the node chosen, here its own outlet AH1, at 6.9 barg. The hose valve behind it is shut (the valve's Status) until a case opens it.

The Calculator holds the pump's net pressure, the discharge PD less the suction PS, and that net pressure as a percentage of the rated 10.3 bar - NFPA 20's measure.
12.6 Calculation procedure#
- Draw the model of Figure 173 and press Run: the standpipe demand.
- Open Scenario, type Sets, with the inputs the Flow In at TH, A8, A7, B8 and AH1 and the Status of PRV-1, and as results the pump flow, the pressures at PD, A8 and A1 and the Calculator's percentage. Type the five cases of Table 26 and press Run.
- Open Adjust: adjusted variable the Relative speed of FP-1, target the Pressure of A8, value 6.9 barg. Press Start; do not apply it - it measures a margin.
| Case | What it is | Test header | A8, A7, B8 | Floor-1 hose valve |
|---|---|---|---|---|
| 1 | Churn: the pump running against shut valves | 0 | 0 | shut |
| 2 | Rated flow through the test header | 2839 | 0 | shut |
| 3 | 150 % of rated flow | 4259 | 0 | shut |
| 4 | The standpipe demand | 0 | 946 each | shut |
| 5 | The first-floor hose valve alone | 0 | 0 | 946, through PRV-1 |
12.7 Reference results#



| Requirement | Limit | FlowMax | |
|---|---|---|---|
| Churn pressure, % of rated (NFPA 20) | ≤ 140 | 120.0 | met |
| Rated flow, % of rated pressure | 100 | 100.4 | |
| 150 % flow, % of rated pressure (NFPA 20) | ≥ 65 | 68.1 | met |
| Pressure left at A8 with the demand (NFPA 14) | ≥ 6.9 barg | 7.39 barg | met |
| Pressure at the first-floor hose valve, churn (NFPA 14) | ≤ 12.1 barg | 12.54 barg | exceeded: a pressure-reducing valve |
12.8 Interpretation#
At churn the pump gives 12.61 barg, 120.0 per cent of its rated net pressure; at 150 per cent of its rated flow, 68.1 per cent. Both are inside NFPA 20. With the standpipe demand the pump runs at 2838 L/min - its rated flow - and A8, the most remote outlet, is left with 7.39 barg, 0.49 bar above what NFPA 14 asks.
The lowest outlet sees the most. At churn, with nothing flowing, A1 is at 12.54 barg - the pump's churn pressure plus the tank's level, less 1.2 m - and that is above the 12.1 bar NFPA 14 allows at a hose outlet. In case 5 PRV-1 holds the outlet at 6.9 barg while A1 behind it stands at 12.35 barg.
12.9 What-if investigation#
A pump loses head as it wears. Adjust finds the speed - standing for a worn impeller - at which A8 is just at 6.9 barg with the standpipe demand: 0.981 of the rated speed. Head goes as the square of speed, so a pump that has lost 3.8 per cent of its head already leaves the building short of NFPA 14's pressure. That is a thin margin: a designer would choose a pump with more in hand, and the annual flow test of NFPA 25 is how the owner finds out before a fire does.

12.10 Comparison#
Two checks by hand. At churn nothing flows, so the pressure at A8 is the discharge pressure less the static head of the 28.7 m between them: 12.61 - 2.81 = 9.80 barg; FlowMax gives 9.80. With the standpipe demand the 6 in. pipe from the pump room header to A8 loses, by NFPA's formula, 0.137 bar in H-B, 0.118 bar in H-A, 0.054 bar up to A7 and 0.002 bar to A8, 0.312 bar in all; FlowMax's friction over the same path is 0.312 bar.
12.11 Engineering remarks#
- NFPA 20's points are for the pump alone; the acceptance test is made through the test header, and the flow there is measured, not set. In the scenario the flow is given and the pressure found, which is the same test read the other way.
- A tank at grade gives the pump a small positive suction head here. A pump that lifts from a pond or the sea is checked for NPSH as in Example 9.
- Pressure-reducing valves on hose outlets are listed devices with their own minimum flow and pressure; their setting is checked on site with the flow test.
- A jockey pump keeps the system full and at pressure when there is no fire; it is off in every case here.
12.12 Exercise#
The building is raised to twelve storeys, the highest hose valve 45.2 m up. Does the pump still meet the standpipe demand? If not, find with Adjust the rated pressure it would need, and say which floors then need pressure-reducing valves.
Verification checklist#
Every result quoted in the manual was produced by FlowMax while the manual was being assembled, from the project files delivered with it, and every figure is a FlowMax window or sheet painted from the same files. The items below are the things that were NOT verified against an outside source and should be confirmed before the manual is relied on for project work.
| Example | Item | Status |
|---|---|---|
| 4 | Sizing limits 2.5 m/s and 0.004 bar/m; vessel pressure 3.0 barg; coil and chiller pressure drops | Assumed, typical of practice. Not from a project. |
| 5 | Route elevations every 6 km; pump curves; throughput 400 m³/h | Invented for the example. |
| 6 | Hydrant, monitor and deluge demands; 7 barg minimum at the deluge valve | Assumed. To be taken from the fire protection design basis. |
| 7 | Density 10.2 L/min/m², nozzle K factors, the limits in the Design rules window | As seeded in the program from NFPA 15. Confirm against the edition in force. |
| 7 | Equivalent lengths of fittings | The program's table in fitting_spray.txt, after NFPA 13. Not re-checked against the standard here. |
| 8 | LNG properties from -165 to -150 °C | Added to the fluid library for this manual as typical lean LNG. Not from a composition. |
| 8 | Stainless Steel roughness 0.015 mm | Added to the material library for this manual; a common handbook value. |
| 9 | Pump curve and NPSH required curve; 0.6 m NPSH margin | Invented for the example, of realistic shape. |
| 10 | Ordinary Hazard Group 2, 8.1 mm/min over 139 m², K80 sprinklers, the town main's flow test, 950 L/min hose allowance; the alarm check valve as a swing check of the NFPA table | Assumed for the example. To be taken from the hazard classification, the listing and a witnessed flow test. |
| 11 | 10.2 L/min/m² on the drum, K57 nozzles, deluge valve Cv 200, 7.0 barg at the take-off | Assumed. The valve's listed loss and the ring main calculation on a project. |
| 12 | The fire pump's curve (churn 120 %, 68 % at 150 % flow); the building's heights | Invented to meet NFPA 20; not a vendor's curve. |
| all | Fitting K factors | The program's library (fitting.txt). Typical values; not vendor data. |
| Item | Status |
|---|---|
| Results against hand calculation or another program | Examples 10 to 12 are checked by hand in their Comparison: NFPA 13's step by step, ISO 5167-2 for the orifice, static head. Examples 1 to 9 are self-consistent FlowMax results; the Liquid Validation report compares the program with published cases. |
| Screens | Painted by the program off screen at the size each window opens at, in the program's own look. Not photographs of a running session; a window may differ by a pixel or two in its frame. |
| Step-by-step instructions | Written from the program's source and its windows. Each tool was driven through its own buttons to produce the results, but the steps were not walked through by a person at the keyboard. |
| Exercises | The answers quoted in Examples 1 and 2 were worked with the program. The other exercises were checked to be solvable in outline only. |
| Licence | Every model has 33 elements or fewer and was run with the Lite limit of 35 in force. |
| What was wrong | Where it showed |
|---|---|
| Pump power was worked out from the previous run's efficiency; a pump that was off reported an infinite head | Examples 2, 6, 9 |
| A flow set point beyond the pump curve could return a nonsensical solved state | Example 8 |
| Pipe sizing read rounded diameters and Apply wrote them, leaving the old outside diameter | Example 4 |
| Pipe sizing started with its limits set to Individual while showing All pipes | Example 4 |
| Calculator: after a run, var10 and above took the value of var1 | Example 6 |
| Path graph: every point was plotted at the next pipe's length | Examples 5, 8 |
| Scenario and Adjust on fluid temperature stored library properties without converting units; in barg every NPSHa was 10 m low | Example 8 |
| Nozzle Layout: inserted fittings were filed under the pipe's row, not its name, and were not written as equivalent lengths, so in Hazen-Williams they counted for nothing | Example 7 |
| A non-return valve held shut behind a stopped pump could be reported as an error | Example 9 |
| Labels: NPSHa, Required flow and nozzle Pressure lacked a bracket; Adjust's table was titled Iteration Graph_path | Scenario, Adjust, Calculator windows |
| Schedules 40, 80, STD, XS, 40S and 80S had no 1-1/4, 2-1/2, 3-1/2 or 5 in. size (revision 3) | Examples 10, 11 |
| The NFPA calculation of the report left the tees and elbows drawn on the sheet out of a pipe's Le, and its friction of a metre was over L alone (revision 3) | Example 10 |
| Addition | Why |
|---|---|
| A warning, NPSHa is lower than NPSHr, when a pump's curve carries NPSH required and the NPSH available is below it at the running flow | The solver already worked NPSHr out at the duty flow and nothing used it. Example 9 depends on it. |
| LNG in the fluid library; Stainless Steel and Copper Nickel 90-10 in the material library | So that Example 8 uses library data. |
| Observation | Effect |
|---|---|
| The text on the sheet is drawn at the zoom of the session, not of the drawing. A project opened after another, or saved while zoomed, shows its labels and tables at a different size relative to the pipes. | Tables placed side by side can overlap after reopening. The examples were saved at 100 %. |
| NPSH required at the running flow is used for the warning but is not shown in the table of the selected element or the Links table. | The reader takes it from the pump chart. |
| A scenario case or an Adjust step that cannot be solved shows the previous or an impossible value rather than a message. | Examples 3 and 5 say how to recognise it. |
| Adjust takes a first step sized from the slope at the start; on a steep curve it can step outside what is solvable and report Failed. | Choose a target that varies smoothly, as the examples do. |
| In the Nozzle Layout window at its opening size the Auto layout and Design rules buttons are partly hidden by the bottom bar. | Cosmetic. |
| The Insert dialog describes a Grid as Branches tied at both ends, draws it with a main at each end and counts a looped main. What is inserted has one main, with each branch ending at its last nozzle. | Example 7 describes what is inserted. The wording of the dialog is left for a decision. |